So I am staying in a hotel in Denver, overlooking their newest light rail line. I see rails in place and the overhead up but not trains yet. What is the status?
dd
So I am staying in a hotel in Denver, overlooking their newest light rail line. I see rails in place and the overhead up but not trains yet. What is the status?
dd
Running test trains now on some sections for about a month now. Still surfacing south of I-225 towards C470. In service end of next summer.
From the black glass tower, 8th floor I-225 at DTC Pkwy (I-225 @ I-25, Exit 2) [#welcome][#welcome][#welcome] (thanx for bringing the snow!)
Assume you (dd) are at I-25 & Bellview
Yes, DTC merriott – thanks. I was hoping it would be in operation by now.
dd
Surfacing equipment is all south of where you are at. You may still see a speed swing dragging a small ballast car past your window at times. Test cars are still crawling around a 5 mph looking for places where the catenary and the pantographs do not maintain the proper clearance.
Welcome to the neighborhood.
We sometimes forget that railhead to catenary is just as important as rail ot rail.
dd
Really amusing to watch when there is no contact and the internal car battery isn’t installed yet or is cut out.[:D]