LIRR Double-track project


Double Track Completion on the Horizon: Final Phases of Work Begin
Most Work to Take Place During Off-Peak Hours; Some Peak Train Schedules Also Affected

The highly anticipated Double Track Project is entering final phases of work this spring, as Long Island Rail Road crews
ready the infrastructure for its expected completion by end of summer.
Beginning Monday, April 30, through Friday, May 18, 2018, LIRR crews will work around-the-clock to connect
new track to the existing second track west of Central Islip Station, while installing a third rail in that same area.
Pre-testing of the signal system at Central Islip will take place during the first week, while the cutover is planned
for the weekend of May 5-6. Con