[:)]
Going out on a limb here.
Assumptions. Great Plains only, no mountains. Most work can go in parallel with a separate contractor working every few miles. Two shifts/six days (leaves room for solving problems). Another railroad intersects at least every 50 miles, meaning that the longest track-laying stretch is 25 miles.
Computer design using geodetic databases and prepare contracts for below - 1 mo
Detailed surveying, electrical design, communications design - 1 mo
Local contractors make cuts and fills, prepare roadbed, build bridges over streams and roads, install and string poles and wires, install and test communications - 3 mo
Medium size bridge like for Arkansas River or Red River - 12 mo after detailed surveying
Large bridge like for Mississippi River or Missouri River - 24 mo after detailed surveying.
Lay asphalt bottom layer - 1 mo
Lay ballast - 1/2 mo
Put down ties, rail, turnouts and signals installation - 1 mo
Tamping, final ballasting - 1 mo
Testing - 1 mo
Total - 9 1/2 mo not counting medium and large bridges. If you have a medium bridge, then that’s the long pole at 12 mo, leading to 14 mo total. If you have a large bridge, then it’s 26 mo total.
However, this project may stress the supply of ties and rail. You may not be able to get all the ties and rail delivered until 9 mo after order. That would add 4 mo to the 9 1/2.
So, my best guess is 14 mo if you have a medium bridge or only small bridges, or 26 mo if you have a large bridge.
[:)] [:)]